利雅得水泥厂石灰石预均化堆场施工方案
Riyadh Cement Company
Limestone Preblending Stockpile Construction Scheme
说明: Instructions:
该方案编制依据: This Scheme is compiled according to:
1、 石灰石预均化堆场施工图纸
Drawings for limestone preblending stockpile
2、 总承包合同要求
Requirements of General Contract
3、 施工现场环境、机具,施工经验等
Site environment, equipments, and our construction experiences
4、 建筑施工手册(第四版)
Construction Manual (fourth edition)
一、 工程概况 Brief Introduction of the Project
1、工程性质和作用
该工程为利雅得水泥厂石灰石预均化堆场, 其功能是储存和运输石灰石,
建筑工期:土建部分计划 92 天。质量要求:土建工程范围是按照业主提
供的文件所进行的交钥匙模式施工,在施工的每一步都要业主的质量认
可,达到业主的满意。
Nature of the Project and its function
The Project is the limestone preblending stockpile of Riyadh Cement
Company whose function is to store and transport limestone, and the time
limit for the foundation is 92 days. Quality requirements: The Civil Works
Scope is a Turnkey pattern executed as per the documentations offered by the
Owner with each step to be approved by and to the satisfaction of the Owner.
2、建筑的结构特征
该工程主要由网架基础、堆取料机轨道基础和石灰石运输廊道组成,网
架基础由 40 个钢筋混凝土基础组成的半径为 56m 的环形基础,基础之间
用基础梁连接,供上部施工金属网架。堆取料机轨道基础是半径为 51m
的环型钢筋混凝土基础,基础底宽 1.2m,高 1.3m,设置 8 道混凝土后浇
带以降低混凝土收缩应力,基础上部设计有预埋螺栓,用于堆取料机轨
道的安装。石灰石运输廊道为本工程施工的重点,其主要部位是位于场
内的箱体结构进料仓,外部结构尺寸;高 11m,宽 8m,长 40.5m ,壁厚
1m,底标高 -11m,局部 -12m,因为是地下工程,施工时要考虑防水,防
潮措施。
Structure Characteristic of the Construction
The Project consists of net frame foundation, stocking and reclaiming track
foundation and limestone belt conveyor. The net frame foundation is made up
of 40 reinforced concrete foundations. The foundations will be connected