Professional Level – Options Module 4
Advanced Financial P
Management
Thursday 10 June 2010 r
e
p
Time allowed
Reading and planning: 15 minutes
Writing: 3 hours a
This paper is divided into two sections:
Section A – BOTH questions are compulsory and MUST be attempted
Section B – TWO questions ONLY to be attempted
Formulae and tables are on pages 6–10. P
Do NOT open this paper until instructed by the supervisor.
During reading and planning time only the question paper may
be annotated. You must NOT write in your answer booklet until
instructed by the supervisor.
This question paper must not be removed from the examination hall.
The Association of Chartered Certified Accountants
Section A – BOTH questions are compulsory and MUST be attempted
1 The Seal Island Nuclear Power Company has received initial planning consent for an Advanced Boiling Water Reactor.
This project is one of a number that has been commissioned by the Government of Roseland to help solve the energy
needs of its expanding population of 60 million and meet its treaty obligations by cutting CO emissions to 50% of their
2
2010 levels by 2030.
The project proposal is now moving to the detailed planning stage which will include a full investment appraisal within
the financial plan. The financial plan so far developed has been based upon experience of this reactor design