PDOC-476-CTRU-06 Rotating equipment installation procedure
Client
PETRODAR OPERATING COMPANY LIMITED PMC:
Contractor
CHINA PETROLEUM
ENGINEERING CONSTRUCTION CORPORATION DOCUMENT No.:
PDOC/476-CTRU-06 CONTRACT No: PDOC/23/06-476
GUMRY Field Production Facilities Project ROTATING EQUIPMENT INSTALLATION PROCEDURE REVISION RECORD Rev. NO. Submission Date Revision Details Prepared By Approved By OWNER A 2007-9-23 Submitted for reviewed Li Yonggang CONTENTS
Scope
Reference Documents
General
Rotating equipment installation
Pumps
Packaged Compressors
Installation of Crane
Quality record and review reports
Revision note
1.0 Scope
To define and establish procedures for on site handling, movement and installation of mechanically rotating equipment.
Reference Documents Approved for Construction Engineering Drawings
Piping Instrument Drawings PID
Piping Arrangement Drawings
Isometric Drawings
Piping Support Pilling Layout Drawings
API Std 610 Seventh Edition, February 1989-Centrifugal Pumps for General Refinery Services
API Std 674 Maximum Allowable Speed Rating for Power Pumps in Continuous Services
API RP 521 Guide for Pressure Relieving and Depressuring System
Project Standards, Codes Specifications
PDOC-SP-MEC-039 Specification for Multiphase Pumps
PDOC-SP-PIP-002 Specification for Piping Design and Layout
PDOC-SP-CIV-011 Specification for Piling Installation
Project Quality Plan
Vendor Installation Manuals
Materials Handling Procedure
3.0 General 3.1 Foundations shall be completed and checked for correctness and levelness as per drawings and specifications. Prior to installation, foundation shall be clean with correct anchor boltholes location, centerlines marked, elevations and levels established for correctness. Shimming and wedging shall be carried out as per drawings and specifications. 3.2 As required, perform on-site installation of the various equipments as per approved construction drawings and specifications, and instruction by a manufacturer/vendor representative. 3.3 Final insulation jacketing