SECTION 01 00 00GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 GENERAL INTENTION 1
1.2 STATEMENT OF BID ITEM(S) 2
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR 2
1.4 construction security requirements 2
1.4 FIRE SAFETY 5
1.6 OPERATIONS AND STORAGE AREAS 7
1.7 ALTERATIONS 11
1.8 INFECTION PREVENTION MEASURES 12
1.9 DISPOSAL AND RETENTION 15
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS 15
1.11 RESTORATION 17
1.12 LAYOUT OF WORK 17
1.13 As-Built Drawings 18
1.14 USE OF ROADWAYS 19
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT 19
1.16 TEMPORARY USE OF EXISTING ELEVATORS 20
1.17 TEMPORARY TOILETS 20
1.18 AVAILABILITY AND USE OF UTILITY SERVICES 20
1.19 NEW TELEPHONE EQUIPMENT 22
1.20 TESTS 22
1.21 INSTRUCTIONS 22
1.22 HISTORIC PRESERVATION 23
SECTION 01 00 00GENERAL REQUIREMENTS
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Install HVAC Systems for Building 1 3rd Floor as required by the contract drawings and specifications.
Work includes the removal and installation of the HVAC systems located in Building 1 of the St. Cloud VA Medical Center. Work shall include but will not be limited to electrical, plumbing, masonry work, general construction, structural framing and certain finishes. All work shall be coordinated and approved by the project COTR and shall be constructed as according to all specification and drawings.
B. Visits to the site by Bidders may be made only by appointment with the VA Health Care Center Contracting Officer and are strongly recommended.
C. Offices of Image Group, as Architect Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by C
您可能关注的文档
- retainingwall-e-govlink.doc
- retrievalofatmosphericinversionsusinggeostationaryhigh( retrievalofatmosphericinversionsusinggeostationaryhigh).doc
- reviewandrefinementsofthe我m p r o v eequationforestimating( reviewandrefinementsofthe i m p r o v eequationforestimating).doc
- reviewarticle-journalofevolutionofmedicalanddental.doc
- reviewofoccupationalhealthandsafetyunitstandard497.doc
- reviewoftcothinfilms-tau.doc
- riskassessment-broadstonegroupinformationpack.doc
- riskassessmentreport-u.s.departmentofhousingandurban.doc
- rispls剖面图01( section01-rispls).doc
- riverrestorationthefuzzylogicofrepairingreaches.doc
- s e c t i o n018111 - u s t i n b l e d e s i g n r e q u i r e m e n t s( s e c t i o n018111- s u s t a i n a b l e d e s i g n r e q u i r e m e n t s).doc
- s e m1成像-加利福尼亚大学riverside( s e m1 imaging- universityof california, riverside).doc
- s o p c灾害管理单元(d m u)是( the s o p a c disaster management unit( d m u)iscurrently).doc
- s o r c e t b瓦尔卡梯尔国防研究机构a4 -我卫星任务( s o r c e a t b drev a4- a i m satellite mission).doc
- s t e r 用户手册-大学西安大略( a s t e r users handbook- universityof western ontario).doc
- s_300_349.doc-stealthskater.doc
- s5serviceportfoliospecifications-kpn.doc
- sa.1345-methodsforpredictingradiationpatternsoflarge.doc
- safetyandhealth-victoriauniversityofwellington.doc
- salmonellaclassroomcasestudy.doc
文档评论(0)