化工项目试车工作流程要点
* * 热试车期间的指挥调度和监督Coordination and Supervision during Hot-commissioning 此阶段在装置现场实地的双重监督是必不可少的 Additional personnels, both supervisory and “on the-ground” are required at this stage; 试车管理人员和业主装置管理人员间的合作是至关重要的 Cooperation between commissioning personnel and plant supervisory personnel is critical at this stage: 每天至少一次的例会制度 Need a daily meeting at least; 经常性的班前、班后会 Often, a briefing each shift. 故障诊断Trouble Shooting 在此阶段 ,许多设备问题将显现出来 At this stage, many problem with equipment of the process itself may become apparent; 试车过程一般都会经历一个高频的(希望是短暂) 所谓“故障诊断、解决方案、工程修改和装置改造的过程” The commissioning process go