- 1、本文档共6页,可阅读全部内容。
- 2、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
- 3、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 4、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 5、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 6、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 7、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 8、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
Schedule management
(a) mechanical and electrical engineering project construction plan as a whole
Should be formulated by owner or owner entrust the overall contracting units, but must obtain confirmation approved by the employer.
1. The overall construction plan to inform various cooperated-builing subcontractors, shall be borne by the subcontractors according to the overall planning of a unit or individual project of total schedule or annual construction schedule. Prepare the plan to conform to the requirements of the time schedule specified in the contracts, and overall contractor for examination, verification and confirmation.
2. The overall contractors to review all subcontractors shall timely report the various construction progress plan, review of the report is based on the plan is in line with the overall construction goal request, if there is any discrepancy report to inform the subcontractors shall clarify or amend, if no objection to record in written documents or to negotiate.
(2) the implementation of the plan should be tracking, supervision and inspection, reporting mechanism, and effectively correct the deviation in plan execution
1. The overall contracting units to set up comprehensive dispatching institution, implement schedule of inspection measurement, found the deflection; Should promptly called dispatch meetings, to jointly by all subcontractors, analyses factors that influence the progress to take corresponding countermeasures, in the subsequent construction of useful corrective or alleviate the deviation of progress plan execution.
2. The countermeasures mainly include operation adjustment, the intensity of supplies, mechanized operation ratio adjustment, operating divisions or timing, these should be made by the general contracting unit scheduling mechanism reasonably scheduling decisions.
(3) take measures to ensure schedule implementation
The overall contractors to use the progress payment amount the economic means, correct measu