2012浙大《建设项目管理》在线作业(国外英文资料)
2012浙大《建设项目管理》在线作业(国外英文资料)
Construction project management in zhejiang university
One, single choice (24 questions, 48 minutes). Score: 48
(1) it is a comprehensive guarantee for all kinds of construction projects
A. building engineering all risks
All risks for the installation of the project
Cargo transport insurance
D
The correct answer: A
The unit that bears full responsibility for the construction plan is ()
Supervisor unit
Design unit
Audit unit
Investment unit
The correct answer: B
Project implementation activities (), are the main content of the project plan, and are the foundation for other planned work.
Resource planning
Plan B
Capital plan
Cost plan
The correct answer: B
The minimum control period of an engineering project is associated with the total period of time, usually over a year, under the control period ().
A. season
In B.
C. double week
Week of D.
The correct answer: B
Apply to large complex projects; The company undertakes multiple projects at the same time; The organizational form of a project where the company requires high utilization is ().
A. functional organization
B. pure project organization
C. Matrix project organization
Department of the ministry of commerce
The correct answer: C
6. Risk analysis is refers to the application of various techniques (), using qualitative and quantitative or a combination of both the process of dealing with uncertainty
A. risk analysis technique
B. uncertain technology
C. probabilistic analysis technique
D. deterministic analysis techniques
The correct answer: A
The construction project management plan is the () document that directs the project management.
A. the operational
B. a programmatic
C. job sex
D. sexual
The correct answer: B
The core task of building project management is the project ().
Goal planning
Goal ratio
Target control
Target argument
The correct answer: C
In the network diagram, it is strictly forbidden to start from a single node, and then return to the loop of the original starting po