工程监理细则(Project supervision rules)
Supervision rules for water supply and drainage
1. Outdoor water supply engineering
1) check the quality certificates of various pipes and valves to ensure that unqualified materials and equipment are not allowed to enter the site.
2) the coordinate and elevation of the water supply pipeline shall comply with the design requirements, and the deviation shall not be greater than 50mm, and the allowable deviation shall not be greater than 30mm.
3) the groove middle line, bottom elevation, width, bottom width and slope of water supply pipeline should meet the design requirements.
4) welding of welded steel pipe shall conform to the design specification, and the welder shall have the welding certificate.
5) embedded steel pipe, open steel tube and metal stand should be respectively embalmed and painted.
6) the structure of the socket and the used filler of the feed cast iron pipe shall comply with the design requirements and construction specifications.
7) pipeline foundation should be used according to the design requirements of natural foundation, the sand, concrete pile foundation or basis, such as the design requirements, should according to the actual situation, using the basis of the rational form.
8) the water supply pipeline shall not pass through the sewage structure, and the vertical and horizontal spacing of pipes and sewage pipes shall conform to the design and construction specifications.
9) the test pressure length of the water supply pipe shall not exceed 1000 meters, the experimental pressure and the allowable penetration shall conform to the acceptance standard and fill in the concealed works acceptance record.
10) flushing should be disinfected water supply pipe installation is completed, after water rinse, in-line water 24 hours, by the construction unit for water testing, testing is not qualified disinfection, such as unqualified, it must be disinfected.
11) the requirement of the backfill of water supply pipe can be
您可能关注的文档
- 巴氏奶与普通奶的区别(The difference between buttermilk and regular milk).doc
- 巴勒斯坦旅游旅行攻略(Travel guide to Palestine).doc
- 帮你认字(To help you read).doc
- 巴西ncm 号码(Brazil NCM number).doc
- 帮助我们祛湿的食物(Help us eat clearing damp).doc
- 布法罗旅游指南 (buffalo guide) - 纽约州出境游指南 yododo 游多多(Buffalo guide - New York state travel guide yododo Tours).doc
- 布料机在水泥混凝土路面摊铺施工中的应用_石磊(Application of cloth machine in cement concrete pavement paving construction).doc
- 布料基本知识(Fabric basics).doc
- 布鲁氏菌病防治技术规范(Technical specification for brucellosis).doc
- 布什在林肯号航空母舰上的讲话(Bush's speech on the uss Abraham Lincoln).doc
文档评论(0)