工程造价中易遗漏的一百项(100 items that are easily omitted in the project cost)
1. Drain holes in the insulation roof of the flat roof
2. Embedded iron in stair railing
3. Scaffold for paint and paint construction
4. Precast slab concrete: concrete, transportation and installation of plate and beam seal
5. Bored piles: drilled into the depth of the rock (the project has a large difference in the contents of municipal and road quota projects)
6. The purge of the installation of indoor piping is easy to miss
High cost of outdoor piping installation
8. The installation of Angle steel and the cost of its main materials
9. The coefficient of single - sided soil abandonment is easy to miss
10. The artificial coefficients of the outer soil are forgotten
11. The list of cables, wires, etc. Is only to provide net engineering quantity, and it should also be added with the allowance, bending, loss and so on in group price
12. The basic steel section in the distribution cabinet installation list is easy to leak
It is easy to leak the casing in the pipe installation list
14. Air pipe through the wall
15. Control valve test to flush temporary control for installation.
16. Equipment installation equipment amortization.
17. The flange mounting bolts in the process pipeline are unpriced materials.
18. Installation part: the base of the increase fee of the high-rise building includes the total labor cost of 6 floors or less than 20m. When the high-rise buildings are in accord with the high construction conditions, the increase of the higher construction fee and the high increase fee are superimposed.
19. Roof line and cover plate! Mostly scattered parts!
20. Some scattered and small components are easy to leak;
21. There are gaps in the roof, especially in the heat insulation layer. The cement mortar has a split seam in the horizontal layer, and the seam is also divided on the insulation board.
22. It is also easy to miss the requirements of some specifications, such as: when the wall is longer
您可能关注的文档
- 巴氏奶与普通奶的区别(The difference between buttermilk and regular milk).doc
- 巴勒斯坦旅游旅行攻略(Travel guide to Palestine).doc
- 帮你认字(To help you read).doc
- 巴西ncm 号码(Brazil NCM number).doc
- 帮助我们祛湿的食物(Help us eat clearing damp).doc
- 布法罗旅游指南 (buffalo guide) - 纽约州出境游指南 yododo 游多多(Buffalo guide - New York state travel guide yododo Tours).doc
- 布料机在水泥混凝土路面摊铺施工中的应用_石磊(Application of cloth machine in cement concrete pavement paving construction).doc
- 布料基本知识(Fabric basics).doc
- 布鲁氏菌病防治技术规范(Technical specification for brucellosis).doc
- 布什在林肯号航空母舰上的讲话(Bush's speech on the uss Abraham Lincoln).doc
- 2023咸阳职业技术学院招聘笔试真题参考答案详解.docx
- 2023四川化工职业技术学院招聘笔试真题及参考答案详解.docx
- 2023哈尔滨职业技术学院招聘笔试真题及参考答案详解.docx
- 2023商洛职业技术学院招聘笔试真题及答案详解1套.docx
- 2023呼伦贝尔职业技术学院招聘笔试真题参考答案详解.docx
- 2023南阳农业职业学院招聘笔试真题参考答案详解.docx
- 2023天津公安警官职业学院招聘笔试真题带答案详解.docx
- 2023年上海电机学院招聘笔试真题参考答案详解.docx
- 2023年四川艺术职业学院招聘笔试真题参考答案详解.docx
- 2023安徽体育运动职业技术学院招聘笔试真题及答案详解一套.docx
文档评论(0)