外墙涂料的施工方案(Construction scheme of exterior wall coating)

外墙涂料的施工方案(Construction scheme of exterior wall coating) 5.1 construction of exterior wall coating 5.1.1 construction preparation The substrate requirements: plaster base has been completed and maintained for about 20 days, the alkalinity pH below 9 in the base, at the same time base has been drying (at least 15 days has been dry, humidity is lower than 8%); smooth surface, yin and yang angle and angle line of dense, chiseled walls; no leakage, no cracks, hollowing, foaming problems such as holes structure. No powder, no oil, grease, and other adhesive substances. II. The outer wall reserved jo