Technical code for garden path Engineering (Trial Implementation)
DB33/T1009.7 - 2001
1, general provisions
1.0.1 in order to improve the quality and landscape effects of all kinds of green spaces in our province, according to the relevant standards and the actual conditions of the province, the procedures are formulated.
1.0.2 This procedure applies to the city planning area of all kinds of green land, scenic area road project, is also suitable for the width of 3M, and the radius of the bend strength can meet the access requirements, can use 1.5 tons of small car road design, construction, supervision, quality supervision and management. If more than 1.5 tons of automobiles need to be carried out, they shall be carried out in accordance with the relevant standards of municipal roads.
1.0.3 construction of road works must be based on the relevant examination and approval documents.
While complying with these regulations, the 1.0.4 shall comply with the current state regulations concerning compulsory standards.
1.0.5 where a public green space, residential green space, such as various types of affiliated green space and scenic area with the tour guide, traffic organization, landscape composition function of roads, footpaths and mountain road collectively road.
2, general provisions
2.0.1 garden road construction, should have design drawings. The drawing standard construction drawings, should meet the requirements of regulation.
2.0.2 Garden Road Project (including floor, the same below) should be completed after the completion of the main project and the underground pipeline project.
2.0.3 in the construction of Garden Road, we should effectively protect the original trees and vegetation. All ancient trees or trees with trunk diameter above 15cm should be kept in situ and the road will be avoided. General trees or ridge or move, should be submitted for approval, approval, cons
您可能关注的文档
- 植物景观档(Plant landscape file).doc
- 植物种子传播的方式(The way plants propagate seeds).doc
- 植物种植(Plant cultivation).doc
- 植物科(Plant family).doc
- 植物资料(Plant information).doc
- 植物激素和植物生长调节剂的差别(Differences between plant hormones and plant growth regulators).doc
- 植物志目录(Flora catalogue).doc
- 植物分类表(Plant classification).doc
- 植物保护进展考试题及答案(Plant protection progress examination questions and answers).doc
- 椭圆的几何性质说课教案(Geometric properties of ellipse).doc
原创力文档

文档评论(0)