- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
(此文档为Word格式,下载后可以任意编辑修改!)
文件备案编号:
施 工 方 案
工程名称:
编制单位:
编 制 人:
审 核 人:
批 准 人:
编制日期: 年 月 日
目 录
一、工程概况··········································3
1、深基坑概况·············································3
2、地质情况···············································4
3、平面位置···············································4
二、编制依据··········································4
三、施工计划··········································5
1、施工时间安排···········································5
2、资源投入情况···········································5
四、工艺方法··········································5
1、总体设想···············································5
2、施工流程···············································6
3、围堰施工···············································6
4、河边桥台开挖支护方法···································6
5、陆地基坑开挖支护方法···································7
6、钢板桩施工·············································7
7、土方开挖···············································8
8、基坑排水···············································9
9、砼结构物施工···········································9
10、钢板桩拔除············································9
五、设计计算··········································9
1、陆地基坑围护计算·······································15
2、河边基坑围护计算······································18
六、安保措施··········································9
1、组织体系建设···········································9
2、沉降监测控制··········································10
3、安全文明措施··········································10
七、其它事项·········································11
1、其它辅助方法··········································11
2、沉木河桥0#台第四幅基坑································11
3、加强与水务部门、地方政府的联系沟通····················12
一、工程概况
1、深基坑概况
瓯海大道西段快速路工程Ш标段全长1061m(k4+124~k5+185),主要为高架桥梁、地面桥和地面道路等,涉及深基坑的承台和桥台位于半塘河、沉木河、中横河等三座桥梁处。
沉木河桥桥台基底标高-1.30m,老河道标高为+1.5m,台后标高为+3.6m。基坑开挖深度4.9m;
中横河桥桥台基底标高-1.30m,老河道标高为+1.4m,台后标高为+3.4m。基坑开挖深度4.7m;
半塘河桥台基底标高-1.30m,位于旱地,台后标高为+5.2m。基坑开挖深度6.5m;
具体位置和开挖深度如下:
部位
结构物平面尺寸
开挖深度
数量
墩位
中横河桥
5.8×3