1;2;3;4;5;6;7;8;9;Example: $ 600k ProjectWork Breakdown Structure with Work Package Budgets;11;12;13;14;;16;17;举例 ;19;20;21;22;23;24;25;;27;28;29;30;Packaging Machine Project Status as of Week 8;32;33;34;35;36;37;38;39;40;41;42;43;Homework;B. Below is a table of actual costs. What is the cumulative actual cost at the end of week 6? Determine whether there is a cost overrun or underrun. What is causing it?;c. Below is a table of the cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6? Is it good?
d. What is the
原创力文档

文档评论(0)