ptf-101电气整套启动调试方法资料精
平顶山第二发电厂一期
2×1000MW 机 组 工 程
调 试 作 业 指 导 书
PTF-DQ101
电气整套启动调试方案
第 1 页 共 24 页
平顶山第二发电厂一期2×1000MW机组工程调试作业指导书
工程名称 平顶山第二发电厂一期 2×1000MW 机组
机组编号 #1 机组
文件名称 电气整套启动调试方案
文件类型 整套启动
调试项目部
批 准
年 月 日
审 核
年 月 日
编 写
年 月 日
河 南 电 力 建 设 调 试 院 第 2 页 共 24 页
平顶山第二发电厂一期2×1000MW机组工程调试作业指导书
目 次
1 目的············································································································· 4
2 编制依据 ····································································································· 4
3 设备系统简介······························································································ 4
4 调试内容及质量指标·················································································· 7
5 组织分工 ····································································································· 8
6 仪器设备的配置·························································································· 9
7 调试应具备的条件······················································································ 9
8 调试步骤 ··················································································