浅谈转体施工桥梁牵引索P 锚定位的关键施工技术
1 1 2
李家和 王明亮 赵子斌
(1. 云南公投建设集团第二工程有限公司,云南 昆明 650000; 2.中铁八局集团第六工程有限公司,云南 昆明 650051)
摘要:通过分析设计图中牵引索切线的位置关系,调整P 锚的位置来确保转体有富余的角度。
通过大地坐标系定位方法,准确定位牵引索的位置。通过场外统一制作预埋件的方式,确保
了牵引索预埋的精度,保证了力偶平衡。
关键词:转体桥、牵引索P 锚定位、平衡力偶、定位实用技术。
Key construction technology of P anchor location of bridge traction cable in
rotating construction
1 1 2
Li Jia-he ,Wang Ming-liang ,Zhao Zi-bin
(1. The Second Engineering Company of Yunnan Highway Development and Investment Construction Group CO., LTD. Kunming,
650000;2.No.6 Engineering Company of China Railway No.8 Engineering Group CO, LTD.Yun Nan,Kun Ming,650051)
Abstract: by analyzing the position relation of the traction cable in the design drawing, the
position of the P anchor is adjusted to ensure the surplus angle of the rotating body. The
positioning method of geodetic coordinate system, accurate positioning of the rope position.
Through the off-site unified production way to ensure that the embedded parts, cable
embedded precision, ensure the balance of couples.
key words: bridge and cable anchor, P balance moment, positioning practical technology.
一、转体施工桥梁牵引索P 锚定位的关键施工技术
(一)“牵引索P锚”的在转体施工中“角色”意义
所谓牵引索P锚,它是桥梁转体时外部牵引力施力的作用点,是预埋于转台中的一个构
件。通过P锚将牵引索引出转台,为转体的液压千斤顶提供输出牵引力的条件。它还有一个
重要的身份是决定桥梁可以转动的最大角度。换句话说,牵引索一旦预埋完成,转台浇筑后,
转体的最大角度也随之敲定,而且这种工序是不可逆的。工序转换至转体时,若转体角度不
足,则可以说本次转体施工是失败的。因此,牵引索P锚的定位可以称作转体施工的核心技
术,它所扮演的角色之重要性是不可替代的。
(二)跳出设计图的“理论牢笼”
目前,所有的转体设计图都是通过设计软件来完成,而设计软件中的参数是人工录入的。
设计人员在进行设计时,均以简算的理论值为设计依据。例如:2017年6月29日我们所承建
通车的云南武定至易门高速公路马官营特大桥上跨成昆铁路桥工程,是转体法施工,跨越成
昆铁路。设计转体角度118.3°,是目前国内转体角度最大的一座桥梁,如图所示:
图2-1 牵引索平面布置图
图2-1中可以看出,桥梁中线方向与铁路中线方向交角是118.3°,设计理论转体角度