第28卷 第1期 隧道建设 Vol.28 No.1
2008年2月 TunnelConstruction Feb.2008
厦门翔安海底隧道过风化深槽施工
赵太东
(中铁隧道集团成都地铁盾构项目经理部,成都 61000)
摘要:根据厦门翔安海底隧道过风化深槽施工的工程实践经验,介绍了在可能发生灾害性的突泥、突水、塌方和诱发地面塌陷而导
致海水下灌等地质灾害的情况下,如何采取超前地质预报、设置防水闸门、超前管棚及全断面帷幕注浆等施工辅助措施,从而保证
了过风化深槽施工的顺利进行。
关键词:海底隧道;过风化深槽;施工
中图分类号:U459.5 文献标志码:B
TunnelingacrossDeepWeatheredChannel:CaseStudyon
Xiang’anSubseaTunnelinXiamen,China
ZHAOTaidong
(ShieldProjectManagementDepartmentofChengduMetro,
ChinaRailwayTunnelGroupCo.,Ltd.,Chengdu610000,China)
Abstract:OnbasisoftheengineeringpracticalexperienceinthecrossingofthedeepweatheredchannelofXiang’an
subseatunnelinXiamen,China,theauthorpresentssuchassistantconstructionmeasuresasadvancegeologyforecas
ting,waterresistantgateinstalling,largepiperoofconstructionandfullfacecurtaingroutingthataretakenwithsuch
risksasdisastrousmudburst,waterburst,collapse,groundsubsidenceandseawaterinflow.Duetotheabovemen
tionedmeasures,thetunnelcrossesthedeepweatheredchannelsuccessfully.
Keywords:subseatunnel;tunnelingacrossdeepweatheredchannel;construction
1 工程概况及工程地质 风化深槽施工采用“分循环施工分循环支护方
厦门翔安隧道不仅是我国第一座海底隧道,而且 式”进行。每循环施工包括拱腰以上超前大管棚、全
也是我国第一座采用钻爆法修建的大断面海底隧道, 断面帷幕注浆、CRD法洞身开挖及支护等工序。第
具有海底隧道独有的技术难度高和施工风险大的特 一循环施工长度约为30m(含5m厚岩盘止浆墙),挖
点。根据勘察设计资料,该海域段工程地质、水文地质 20~25m,预留5m并做3~3.5m厚的C25混凝土止
条件复杂多变,风化岩面起伏较大,尤其是 F1、F4强 浆墙,之后每循环长度约为25m,挖 15~20m,留5~
风化深槽地段。 10m。注浆完成后,经检验胶体单轴抗压强度在20
-4
强风化深槽地段围岩主要由强风化花岗闪长岩和 MPa以上、地层渗透系数小于10 cm/d时,采用CRD
二长岩脉组成。围岩软弱破碎,节
您可能关注的文档
最近下载
- 2024-2025学年上海市普陀区六年级下学期数学期末试题含详解.pdf VIP
- 制造业企业员工高离职率分析.pdf VIP
- GB50461-2024:石油化工静设备安装工程施工质量验收规范.pptx VIP
- 三江A116火灾报警控制器简易操作规程.docx
- (新版)社会体育指导员理论知识考试题库(含答案).docx VIP
- DB31T 1104-2018 城市轨道交通导向标识系统设计规范.docx VIP
- 2023年浙江省军队转业干部录用考试试题.docx VIP
- 口渴了-朋友帮你.ppt VIP
- Xikong西莱克低温机控制板SHXK814用户手册.pdf
- 爱迪生牛顿大发明攻略.doc VIP
原创力文档

文档评论(0)