目 录
实施性施工组织设计文字说明
第一章 工程概况 ··········································································
第二章 施工准备 ··········································································
第三章 组织机构和施工部署 ··························································
第四章 设备、人员动员周期 ··························································
第五章 主要工程项目的施工方案、施工方法 ·····································
第六章 各分项工程的施工顺序 ·······················································
第七章 确保工程质量和工期措施 ····················································
第八章 冬季和雨季的施工安排 ·························································
第九章 质量、安全保证体系 ··························································
第十章 其他应说明的事项 ·····························································
实施性施工组织设计附表
投入本合同段工程劳力计划表
投入本合同段的主要机械表
本合同段主要材料数量计划表
分项工程进度计划 (斜率图 )
工程管理曲线
施工总体平面布置图
施工工艺框图
分项工程生产率和施工周期表
施工总体计划图
第一章 编制依据
1 、长泰县县道浦角线 D合同段公路改建工程施工招标文件。
2 、长泰县县道浦角线 D合同段公路改建工程施工合同。
3、长泰县县道浦角线 D合同段公路改建工程设计文件和图纸。
4 、交通部颁发的设计和施工技术规范、操作规程、预算定额及《公路工程
质量检验评定标准》 。
5、国家现行各项法律、法规及规定。
6 、当地的气候条件、施工环境及施工现场调查的资料。
7、我单位拥有的科技成果、管理水平、技术装备、队伍素质、机械装备、
财务实力及多年来在公路工程施工中积累的施工经验。
第二章 工程概况
长泰县县道浦角线 D 合同段公路改建工程由长泰城关至十里段马洋中桥及
接线工程( K7+240-K7+680)和( K7+680-K8+200)右侧人行道工程组成,技术
标准二级,水泥砼路面,有中桥 1 座 106 延米,桥梁采用桩基扶壁式桥台,桥
墩为桩基柱式桥墩,上部结构为 6*16 米预应力空心板梁。
第三章 施工准备
施工准备工作是项目施工的重要环节,是控制项目工期、质量的关键工序。
为实现“早开工,开门顺” ,我项目经理部将制定详细的施工准备计划,以指导
施工前准备工作,主要做好以下工作:
1、人员、机械设备进场
人员、机械设备和物质进场, 总原则是根据工程施工进度安排分期分批进场,
并依据情况变化加强调整。第一批人员和机械进场后即开始施工驻地建设和现
场设备、技术