advance 517 Chengdu Metro Line 1 project no.: S-366 page 1 / 3 start end at: 22.03.2015 at: 22:29:04 at: 23.03.2015 at: 01:42:35 time: [hs:min:sec] [hs:min:sec] [hs:min:sec] [hs:min:sec] advance: 01:25:23 ringbuild: 00:48:37 stop: 00:59:40 total: 03:13:30 cutting wheel: average rotation speed [rpm] 1.4 rotating direction left [%] 55 torque [MNm] 2.60 rotating direction right [%] 45 working pressure [bar]