一、单项选择题(共10小题,每题2分)(每小题只有一个选项符合题意,请把正确选项的字母填在题后括号内)
1.Aprojectmanagerisresponsiblefortheoverallplanning,execution,andclosingofaproject.WhichofthefollowingisNOTakeyresponsibilityofaprojectmanager?
A.Developingaprojectcharter
B.Managingstakeholderexpectations
C.Conductingdailyteammeetings
D.Ensuringprojectcompliancewithorganizationalstandards
参考答案:C
2.Inprojectmanagement,thetermscopecreeprefersto:
A.Theprocessofexpandingtheprojectscopewithoutproperchangecont