1.WhichofthefollowingisNOTapartoftheprojectinitiationphaseaccordingtostandardprojectmanagementmethodology?
A.Definingprojectobjectivesanddeliverables
B.Identifyinginitialstakeholders
C.Developingdetailedprojectschedule
D.Conductingstakeholderanalysis
参考答案:C
2.Inprojectmanagement,whatdoesthetermcriticalpathreferto?
A.Thesequenceoftasksthatdeterminestheminimumprojectduration
B.Thepathwiththemostresour