WNC FAT Rport #32_090924_

Wyeth Nutritional (China) Project FAT Report #32 for F17_ EMS/BAS DDC panel-Siemens@ Wyeth SitePrepared by W2a September 2009 Package: F17 EMS/BAS Manufacturer: Siemens Date of FAT: 2009-08-26 Location: Wyeth Site Witnessed by: Wyeth- Fangxin;W2a –Wang Jinfu; MWZ –Liu Deqiang Description: This FAT report is only for for the second batch DDC panel of EMS/BAS ,total 26sets , 20 sets will be installed in Production Building ,5sets will be installed in Warehouse Building, 1 sets will be installed in Chemical Building;all panels have been moved in Wyeth site;M+W think over schdedl