The contractor after receiving the project supervisor instructions change

The contractor after receiving the project supervisor instructions change, think that it is impossible to carry out, should immediately offered cannot perform the change reason for instructions. Contractor that can perform the change, to implement the change should be given written instructions to the effect of the contract price and time limit for a project, and the parties to a contract shall be determined in accordance with the agreement on the change of valuation valuation changes. The contractor after identifiers The project supervisor instructions change, think that it is impossible to c