島根原子力発電所被ばく線量低減対策の検討
Dose Rate Reduction Methods at Shimane Nuclear Power Station Tadashi Kanaoka1, Hiroyasu Kajitani1, Tsuneo Sato1, and Naoshi Usui21The Chugoku Electric Power Company, INC2Hitachi-GE Nuclear Energy, Ltd 0.The location of Shimane NPS and Head office 1.Introduction Shimane Nuclear Power Station Unit 1 continues operating smoothly since commercial operation started in 1974. An increasing trend of the dose rate has been observed since the hydrogen injection was applied at 21st operating cycle (1998) and the dose reduction became the urgent problem. 2(1).Radiation exposure of the outage 2(2).T