Matters neding attention
Matters needing attention
A, before rinsing to rinse solution, advance notice about the main water user.
B, before rinsing check rinse water will affect the safety of the Yangtze river ships, assign personnel to safety monitoring in the process of washing.
8.3.1.10 pipeline anticorrosion
Pipe production is completed on the internal and external anti-corrosion, set aside 100 mm so that the welding pipe jacking pipe end each joint well before after welding pipe jacking, after the interface corrosion in pipe jacking. Pipeline corrosion protection work in strict accordance with the constructio
您可能关注的文档
最近下载
- 基于Glauert法的风力机叶片设计设计说明书论文.docx VIP
- 12J7-3 内装修-吊顶-常用建筑图集.docx VIP
- 《紫苏生产技术规程》DB41T 3072-2025(河南标准).pdf VIP
- 党员组织生活会批评与自我批评发言材料.docx VIP
- 马工程《教育学原理》第十章 复习笔记.pdf VIP
- 柱锤冲扩法柱锤冲扩桩法.pptx VIP
- 浙江国企招聘-2026宁波海创集团有限公司第3批次公开招聘工作模拟试卷(浓缩300题)推荐.docx VIP
- 2025年最新主题教育应知应会知识竞赛题含参考答案.docx VIP
- (2026春新版)苏教版二年级数学下册全册教学设计.pdf VIP
- 浙江国企招聘-2026宁波海创集团有限公司第3批次公开招聘工作考前自测高频考点模拟试题(浓缩300题.docx VIP
原创力文档

文档评论(0)