? Estimating schedule activity costs involves developing an? ( 1 )??of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of? ( 2 )??to facilitate comparisions both within and across projects. The? ( 3 )??describes important information about project requirement that is considered during cost estimating.
(1) A. accuracy??? B. approximation????? C. specification? D. summary
(2) A. activity????? B. work???????????? C. currency????? D. Time
(3) A. project scope statement???????????? B. statement of work
?????C. project management plan??????????? D. project policy
答案:(1) B??? (2) C??? (3) A
[分析]
估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本。成本估算包括识别和考虑各种成本计算方案。例如,在大多数的应用领域中,普遍在设计阶段多做些额外工作以降低执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般以货币单位表示,以利于在项目内和项目间进行比较。项目范围说明书描述了项目的需求的重要信息,这些信息在成本估算时必须考虑。
( 4 )??is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that arrow the dependencies.
??This method includes following types of dependcies or precedence relationships:
?( 5 )??the initiation of the successor activity, depends upon the completion of the predecessor activity.
( 6 )??the initiation of the successor activity, depends upon the initiation of the predecessor activity.
A. PDM?????? B. CPM???????????? C. PERT??????? D. AOA
(5) A. F-S???????? B. F-F????????????? C. S-F????????? D. S-S
(6) A. F-S???????? B. F-F????????????? C. S-F????????? D. S-S
答
您可能关注的文档
最近下载
- 05YJ11-2 住宅卫生间-常用建筑图集.docx VIP
- CECS19-1990 混凝土排水管道工程闭气检验标准.docx VIP
- 高频量化笔试题及答案.docx VIP
- DB23_T 3970-2025 寒区聚氨酯水泥预应力钢丝绳抗弯加固桥梁技术规程.pdf VIP
- 2024年6月全国大学英语CET四级真题和答案解析(全三套).pdf VIP
- 联想移动固态硬盘及U盘产品标准保修承诺.pdf VIP
- 机关业务知识考试科技含答案 .pdf VIP
- 2023年甘肃省定西市八年级学业水平考试——地理、生物学合卷 .docx VIP
- 机关业务知识试卷及答案.doc VIP
- 放射科温湿度记录表供参考.doc VIP
原创力文档

文档评论(0)