余热锅炉事故处理规则(国外英语资料)
余热锅炉事故处理规则
Three point one
Phenomenon of water shortage
3.1.1
Water level is below normal.
3.1.2
The alarm has a low water level signal.
3.1.3
When the water shortage is serious, the superheated steam temperature rises or the temperature decreases and the water quantity increases.
3.1.4
The abnormal flow rate of water is less than the amount of evaporation (water wall tube or economizer pipe rupture, and water supply is greater than evaporation).
Three point two
Reasons for lack of water
3.2.1
The operator was careless and didnt monitor the water level or mistake it.
3.2.2
The malfunction of the water supply automatic regulator was not found in time.
3.2.3
The water level meter indicates incorrect operation of the operator.
3.2.4
Failure of water supply pipe or feed pump makes water pressure drop
3.2.5
Boiler blowdown valve leakage or discharge without contact and fire.
3.2.6
Water wall tube, convection tube or economizer pipe wall rupture.
3.2.7
The isolating valve core falls off on the water supply pipeline.
Three point three
Treatment of water shortage
3.3.1
When the boiler pressure and feed water pressure are normal, while the water level in the drum falls to the normal water level (i.e., slight water shortage), the following measures should be adopted:
A. carries out the comparison of the water level meters and the cleaning of the drum water level gauge to check whether the instructions are correct.
B. will automatically change the water supply to manual operation on the spot and increase the water supply.
3.3.2
As after treatment, the water level in the drum is still very low, should be closed all the boiler drain valve, and check whether the regular discharge valve and drain valve is closed, such as leakage serious, should be shut down the total discharge valve.
3.3.3
If the above measures are taken, the water level will continue to decline and the minimum allowable water level shall be reported to the workshop or the plant in a timely manner, and the boiler
您可能关注的文档
- 世界挖掘机综合实力排行前十(国外英语资料).doc
- 世界末日铁证(国外英语资料).doc
- 世界近代史易混淆概念五十例(国外英语资料).doc
- 业绩再好的员工也会被炒.(国外英语资料).doc
- 世界近代通史(国外英语资料).doc
- 世界近代历史知识(国外英语资料).doc
- 东南路线(国外英语资料).doc
- 东北强力菜谱(国外英语资料).doc
- 东北大学15春学期《管理心理学》在线作业2(国外英语资料).doc
- 东大16秋学期《人力资源管理概论》在线作业1(国外英语资料).doc
- 2-红河州建筑施工安全生产标准化工地复核评分表(2022年修改版).docx
- 6.锡通项目2018年下半年工作会汇报材料(2018.7.9).docx
- 2018道路工程知识点汇总(新版).docx
- 附件3:月度生产例会安全汇报资料-站台门项目部.docx
- 附件2:广东建工集团2018年度科技成果汇总表.DOC
- 马武停车区、三汇停车区停车位管理系统,0#台账缺量.doc
- 攀成钢委办发〔2015〕19号(党风廉政建设责任考核与追究办法).doc
- 1-红河州建筑工程质量管理标准化复核评分表(2022年修改版).docx
- 中交第三公路工程局第四工程分公司项目经济合同结算管理办法(修订).doc
- 厂站安全操作规程汇编.doc
文档评论(0)