土建管理(Civil Engineering Management)
土建管理(Civil Engineering Management)
First, individual choice questions
1. the construction party is a participant of the project, whose project management is mainly subordinated to (and) its own interests.
A. owners interests B. the interests of the construction side
C. design side benefits the overall interests of the D. project
Answer: D
Analysis: the construction party is the participant of the project management, and its project management mainly serves the overall interests of the project and the interests of the design itself.
2. risk amount means ().
A uncertain degree of loss; grade a constructor; qualification for examination
Probability of B loss occurrence
C the size of the economic risk
D the degree of uncertainty of the loss and the probability of loss
Answer: D
The amount of risk refers to the degree of uncertainty of the loss and the probability of the loss.
3., the construction project management planning involves the whole implementation phase of the project, it belongs to () project management category.
A. construction side, B. design party, C. owner, D. Supervisor
Answer: C
Analysis: construction project management planning involves the entire implementation phase of the project, belonging to the owners of the scope of project management.
4., the owner of the construction project design tasks and construction tasks entrusted by the comprehensive model, can be called construction projects.
A. contracting
B. subcontracts
C. general contracting or general contracting
D. joint contracting
Answer: C
Analysis: the general contracting or general contracting of construction projects refers to the mode that the owners entrust the design task book and construction task book of the construction project comprehensively.
5. integrate the project decision-making phase of development management (DM), the implementation phase of project management (PM) and the use of stage facilities management (FM) into projects.
A, whole process management, B, overall management
您可能关注的文档
最近下载
- TBIE 004—2023通孔回流焊接技术规范团标.pdf
- 国开《MySQL数据库应用》形考1-4(试题及答案).pdf VIP
- 煤矿安全生产作业规程操作规程安全技术措施编制审批贯彻及执行管理制度.doc
- 2020年光学膜行业研究报告.pdf
- 采血管种类和应用ppt课件.pptx VIP
- 职业生涯报告六篇.pdf VIP
- Unit 4 Plants arounds us PartA Let's talk(课件)人教PEP版(2024)英语三年级上册.pptx
- 七年级上册生物:必考问答式知识点汇总(背诵+默写).docx
- 《青纱帐——甘蔗林》课件【中职专用】高教版 基础模块下册.pptx
- 国家开放大学学位英语历年真题试卷号1909.docx
文档评论(0)