2.12 Perceptions of Owners and Contractors
Although owners and contractors may have different perceptions on project management for construction, they have a common interest in creating an environment leading to successful projects in which performance quality, completion time and final costs are within prescribed limits and tolerances. It is interesting therefore to note the opinions of some leading contractors and owners who were interviewed in 1984.
From the responses of six contractors, the key factors cited for successful projects are:
well defined scope
extensive early planning
good leadership, management and first line supervision
positive client relationship with client involvement
proper project team chemistry
quick response to changes
engineering managers concerned with the total project, not just the engineering elements.
Conversely, the key factors cited for unsuccessful projects are:
ill-defined scope
poor management
poor planning
breakdown in communication between engineering and construction
unrealistic scope, schedules and budgets
many changes at various stages of progress
lack of good project control
The responses of eight owners indicated that they did not always understand the concerns of the contractors although they generally agreed with some of the key factors for successful and unsuccessful projects cited by the contractors. The significant findings of the interviews with owners are summarized as follows:
All owners have the same perception of their own role, but they differ significantly in assuming that role in practice.
The owners also differ dramatically in the amount of early planning and in providing information in bid packages.
There is a trend toward breaking a project into several smaller projects as the projects become larger and more complex.
Most owners recognize the importance of schedule, but they adopt different requirements in controlling the schedule.
All agree that people are the key to project success.
您可能关注的文档
- Tibco 产品安装手册.doc
- 中国地质大学(北京)考博试题填空答案2000-2011.doc
- 必修3 Module3Period 2 Grammar—The past perfect passive and Indirect speech教案.doc
- 赵红珊Purpose and Tone考题.doc
- 审计风险外文文献.docx
- Guide to university Learning - 上传.docx
- BUSINESS PLAN GUIDE - 原版.docx
- 大学英语四六级常考短语.docx
- 完形填空词组及固定搭配.doc
- ServerGuide-_引导安装指南.doc
- 2024年03月江苏省盐城市射阳县卫生健康委员会直属事业单位校园招聘编制内医学类高层次和紧缺专业人才50人笔试历年专业考点(难、易错点荟萃)附带答案详解 .docx
- 2025年广州铁路职业技术学院单招语文2019-2024历年真题考点试卷含答案解析.docx
- 2025年江苏城市职业学院单招英语2014-2024历年真题考点试卷摘选含答案解析.docx
- 2025年河南轻工职业学院单招英语2014-2024历年真题考点试卷摘选含答案解析.docx
- 2025届北汽集团全球校园招聘正式开启笔试参考题库附带答案详解.pdf
- 2024年03月广东深圳市疾病预防控制中心选聘2人笔试历年专业考点(难、易错点荟萃)附带答案详解 .docx
- 2024年03月浙江舟山市卫生健康委员会部分直属事业单位招聘(第五批)宁波市考点考试笔试历年专业考点(难、易错点荟萃)附带答案详解 .docx
- 2025年泉州工程职业技术学院单招职业技能测试近5年真题考点含答案解析.docx
- 2025年宁夏工业职业学院单招职业适应性测试历年(2019-2024年)真题考点试卷含答案解析.docx
- 2025年首发集团校园招聘开启笔试参考题库附带答案详解.pdf
文档评论(0)