人工挖孔灌注桩施工浅析
人工挖孔灌注桩施工浅析
作者简介:徐灵根,男,1976.12,工程师,本科,从事建筑施工。
摘要:人工挖孔桩有施工方便,质量易控,造价低等优点,同时施工又有劳动强度大,作业环境差,安全事故多等缺点,本文对人工挖孔桩的各主要施工环节结合工程实例作较详细的介绍,提供给广大施工技术人员交流并推广人工挖孔桩的工程应用。
关键词:人工挖孔桩;挖孔桩;灌注桩;干浇法;水下灌注法;护壁
Abstract: the artificial dig-hole pile have construction is convenient, easy to control the quality, cost advantages, and construction and labor intensity big, bad working environment, safety accident many shortcomings, in this paper, the artificial dig-hole piles main construction link with an engineering example for more detailed presentation, provided to the construction technology personnel exchanges and the promotion of artificial dig-hole pile engineering application.
Keywords: artificial dig-hole pile; Dig-hole pile; Filling pile; Dry water law; Underwater perfusion; slurry-supported
中图分类号: U443.15+4文献标识码:A 文章编号:
人工挖孔桩有其施工设备简单,进退场方便;在正常施工条件下质量有保证;对环境污染少;承载力大,布桩容易;造价便宜;应用范围广等优点,同时也有工人劳动强度大,作业环境差;安全事故多;挖孔抽水易引起附近地面沉降、房屋开裂或倾斜;在富含水地层中有时会导致挖孔桩施工失败;低层或小开间多层楼房桩基造价并不便宜等缺点。本文就结合工程实例对人工挖孔桩的开挖、支护、钢筋笼制安、桩身混凝土浇筑控制作阐述。
1.工程概况
云都?凤凰城位于杭州市桐庐县城南云栖中路与学圣路交汇处。总建筑面积约23万平方米,由18幢建筑组成,其中17幢为18~30层高层住宅,局部有1-3层商铺附房等,大面积地下室1层,框架或框剪结构,建筑高度最高为100.6米。本项目结构使用年限50年,建筑桩基设计等级为甲级,基础采用人工挖孔灌注桩,通过地质勘察,分为①杂填土(mlQ4)②粉质粘土(alQ4) ③强风化粉砂岩(Q3c) ④中风化粉砂岩(Q3c)等4个工程地质层,地基土层分布相对稳定。设计以④中风化粉砂岩作为桩基础持力层,勘察院给出的极限侧阻力标准值qsik为400KPa,极限端阻力标准值qpk为9000KPa,设计桩端全截面进入持力层不小于1m,且有效桩长不小于4m,桩径为φ800mm,扩大头直径为1200、1500、1800、1900mm。对应设计单桩竖向承载力特征值为2700KN,3700KN,5000KN,5200KN。桩基及护壁详图见图1。
图1. 桩基及护壁详图
2.施工工艺
人工挖孔桩偏差符合《建筑地基基础工程施工质量验收规范》GB50202-2002,先定桩位后挖孔,挖孔直径比设计桩径大35cm。
施工工艺流程如下:
放线定桩位及高程→挖第一节桩孔土方→检查桩位中心轴线→支护壁模板→放附加钢筋→浇筑第一节护壁混凝土→在护壁上二次投测标高及桩位十字轴线→安装垂直运输架→安装电动葫芦(卷扬机或木辘轳)→安装吊桶、照明、活动盖板、水泵、通风机等→挖第二节桩孔土方→先拆第一节支第二节护壁模板(放附加钢筋)→校核模板垂直度和直径→浇灌第二节护壁混凝土→重复第二节工序、循环作业直至设计深度→检查持力层进行扩底→全面检查桩孔直径、深度、扩底尺寸、持力层→清理虚土、排除孔底积水→吊放钢筋笼就位→灌注桩身混凝土(随浇随捣)
2.1开挖作业
开挖前,应从桩中心位置向桩四周引出4个桩心控制点,用牢固的木桩标定。当第一节桩孔挖好安装护壁模板后,必须校正模板位置,并设专人严格校核中心位置及护壁厚度。开挖采取分段形式,每段高度决定于土壁保持直立不坍状态的能力,一般以0.8~1.0m为一施工段,本项目定为1m,开挖桩孔土方从上到下