浅谈徐洪河浦棠桥灌注桩基础质量控制
浅谈徐洪河浦棠桥灌注桩基础质量控制
摘要:徐洪河浦棠桥主桥采用下承式钢筋混凝土系杆拱结构,基础为灌注桩。在实际施工中,监理部参与到施工单位的质量控制工作中,参照理论与实际经验,不断调整施工方案,对灌注桩各个工序施工的质量进行有效控制,保证了灌注桩的成桩质量。
关键词:灌注桩;测量放样;钻孔;清孔;钢筋骨架;灌注水下混凝土
Abstract: the main XuHongHe PuTangQiao by XiaChengShi reinforced concrete bowstring arch bridge structure, the basis for the pile. In the actual construction, supervision department involved in the construction of the unit control of quality, and referring to the theoretical and practical experience, and constantly adjust construction scheme of filling pile construction quality of each working for effective control, and to ensure the quality of under-reamed bored pile.
Keywords: filling pile; Measuring layout; Drilling; Hole cleaning; Steel skeleton; Perfusion underwater concrete
中图分类号:O213.1文献标识码:A 文章编号:
睢宁县徐洪河浦棠桥改建工程位于睢宁县魏集镇境内的徐洪河上。桥梁基础采用灌注桩基础。桥台灌注桩基础为4根钻孔灌注桩,直径为1.2米,设计底高程-4.0米,顶高程为21.0米,桩间距为横桥向5.2米,顺桥向3.5米。桥墩灌注桩基础为8根钻孔灌注桩,直径为1.2米,设计底高程-7.7米,顶高程为20.3米,桩间距为3.2米。
灌注桩施工由搭设施工平台、设置护筒、泥浆制备、钻孔、清孔、安放钢筋骨架、安装导管、灌注水下混凝土等工序组成,本文着重就灌注桩基础几个重要工序施工中应注意的问题进行总结与探讨。
1 测量放样
桩的测量定位一定要精确,不允许超出规范规定的偏差范围。测量放样过程中利用全站仪反复测量,保证灌注桩的定位准确无误。施工测量人员在放样过程中角度误差控制在1″到2″,平面位置误差控制在2-5mm之间,符合规范要求,保证了桩位的准确。
2 泥浆制备
钻孔时,选用适当的泥浆。本工程根据现场土质情况,在孔深范围内从上往下基本以粉土、粘土为主,往下局部有中粗砂层,采用正循环钻进法施工,钻孔泥浆性能泥浆比重选用1.05-1.20,实际操作基本控制在1.10左??。
3 钻孔应注意的问题及其处理措施
3.1钻机就位
钻机就位应依据测量放样点进行,其偏差不应超过规范要求的范围。钻机安装后的底座和顶端应平稳,在钻孔过程中不应产生位移和沉陷,否则应及时处理。
3.2钻孔作业
钻孔作业应分班连续进行,填写的钻孔施工记录,交接班时应交代钻进情况及下一班应注意事项。
3.3钻孔垂直度校正
首先桩架要垂直安置稳固,其次对导架进行水平与垂直校正和对钻孔设备加以检修,控制钻杆垂直度。从不同方向上吊垂线予以检验和调整,将钻杆倾斜率控制在1%范围内,保证孔的偏斜不超过规定范围
3.4卡钻、掉钻的处理
在钻进过程中,如果过程中发生卡钻、掉钻,采取相应的处理措施。在钻孔排渣、提钻头除土或因故停钻时,应保持孔内具有规定的水位和要求的泥浆相对密度和粘度。处理孔内事故或因故停钻,必须将钻头提出孔外。
3.5扩孔、缩孔的处理
扩孔是由于孔壁坍塌或钻锥摆动过大所致,缩孔原因是钻锥磨损过甚,焊补不及时或因地层中有软塑土,遇水膨胀后使孔径缩小。预防扩孔要注意采取防止坍孔和防止钻锥摆动过大的措施。预防缩孔要注意及时补焊钻锥,并在软塑土层采用失水率小的优质泥浆护壁。已发生缩孔时,宜在该处用钻锥上下反复扫孔以扩大孔径。本工程3#台3#桩在灌注混凝土中计划灌注34方混凝土,实际灌注39方,在高程16-19米用了8方混凝土,而根据设计需用3.6方就够了。经过分析,在高程16-19米出现了扩孔,说明这段可能是砂层或其它地质薄弱层,施工中及时调整方案,在钻孔中时刻留心钻进情况是否异常,经常对钻孔泥浆进行检测