南水北调东线淮安四站输水河道穿湖段工程实施的方案优化
南水北调东线淮安四站输水河道穿湖段工程实施的方案优化
摘要:通过对南水北调东线第一期工程淮安四站输水河道穿湖段工程优化实施方案的分析,提出在湖泊中建设水利工程需注意的施工工期#65380;施工风险#65380;实施方案#65380;投资控制等问题,对今后类似工程的设计和施工可以起到参考和借鉴作用。
关键词:南水北调; 输水河道;实施方案;优化
中图分类号:TV68;TV22 文献标识码:B 文章编号:1672-1683(2007)05-0026-02
Implemental Scheme Optimization on the Water Transferring Canal of Huaian
No.4 Pumping Station, Eastern Route of the South-to-North Water Diversion
LIU Lian-jian SHAN Wen-bin ZHU Li-zhong2
(1.Huai′an Water Resources Bureau, Huai′an 223005, China;2.Huaian Surveying and Design Institute of Water Resources Co., Ltd., Huai′an 223005, China)
Abstract: The article analyzes the implementation scheme of The Huai′an No. 4 pumping station and its water transferring canal on many aspects such as the river-lake connection scheme, scheme optimization on construction, risk controlling during construction, structure of spillage weir, general layout, etc. Also points out the problems that must be paid attention during the implementation of hydraulic structures such as construction period, construction risk, implementation scheme, cost controlling, etc, which can be the guidance for future design and implementation on similar projects.
Key words:South-to-North water diversion; water transferring canal;implementation scheme;optimization
1 引 言
南水北调工程是缓解我国北方地区水资源短缺,实现水资源合理配置,保障经济社会可持续发展,全面建设小康社会的重大战略性基础设施。南水北调东线工程是利用江苏省江水北调工程进行的扩大和延伸。淮安四站及其输水河道工程是南水北调东线一期工程的重要组成部分,属南水北调东线第二梯级。淮安四站输水河道从京杭大运河北运西闸至淮安四站站下线路,全长29.8 km,其中大运河至白马湖段长7.47 km,白马湖穿湖段2.3 km,新河段20.03 km,设计输水规模100 m3 /s,批复总投资2.83亿元。初步设计采用河湖分开,专线送水方案,其中穿湖段工程设计在湖内抽槽,同时在西侧筑隔堤[1]。
2 工程概况
为保证输水水质#65380;输水水量和白马湖湖区生态环境,不影响白马湖地区的排涝#65380;养殖#65380;航运#65380;灌溉等综合功能,淮安四站输水河道在穿湖段隔堤中部新建1座550 m长的排涝滚水堰,设计排涝流量150 m3/s,最大排涝流量250 m3/s。滚水堰在隔堤直线段布置,为梯形断面,堰身结构为混凝土底板#65380;浆砌块石墙身。为沟通隔堤两侧航运,保证向湖区补水,结合白马湖向北运西河投机自排,初设方案在北运西河入湖口布置补水闸1座,兼有通航功能,闸孔净宽8.0 m,设计流量30 m3/s[2]。
穿湖段工程原施工方案为挖泥机船疏浚表层淤泥,然后打坝抽水,采用陆上土方机械筑隔堤和滚水堰。具体说,就是选用抓斗挖泥机船施工,湖中抓土将围堰筑出水面,然后将水抽干#65380;清淤后采用陆上土方机械加固围堰,同时筑