建筑施工组织课程设计
设计名称 汕尾市新闻中心综合大楼
施工组织设计
学 院 工 商 管 理 学 院
专业班级 2011级工程管理4班
学号姓名 1000002060 袁鹏生
指导教师 王学通 于茜薇 谭湘倩
完成日期 2013年12月
目录
工程概况····················································1
施工方案····················································2
2.1主体工程·················································2
2.2起重机械、手脚架·········································2
2.3土石方工程···············································3
2.4模板工程·················································3
2.5钢筋工程·················································4
2.6砼工程···················································4
2.7现场垂直运输与吊装工程···································5
2.8装饰工程·················································5
2.9屋面工程·················································6
2.10特殊部位的施工方法和技术措施····························6
施工进度计划················································6
3.1施工过程的工序项目·······································6
3.2施工工程量计算填表·······································7
3.3劳动量、各施工过程的作业天数和机械台班数·················7
3.4各工程阶段的流水作业·····································7
3.5编制施工进度计划·········································7
3.6绘制日施工总人数变化折线图·······························7
施工平面图···················································8
4.1施工平面图的设计原则·····································8
4.2确定起重机的数量及其位置·································8
4.3砼搅拌站、加工厂、堆放场地的大小与位置···················8
4.4 临时房屋的大小与位置;临时道路和临时水电管网的位置·······8
5.各项技术经济措施·············································8
5.1技术措施·················································8
5.2 质量措施·················································9
5.3 安全措施················································10
5.4 降低成本施工措施········································10
5.5 现场文明施工措施···········