目录
第一章:工日分析···································1
第二章:施工导流计算·······························7
第一节:导流标准···································7
第二节:导流方案···································7
第三节:导流工程规划布置···························8
第四节:大坝分期及安全校核························13
第三章:主体工程施工计算··························16
第一节:土石坝施工································16
第二节:导流洞开挖································20
第一章:工日分析
月有效工日=日历天数-法定假日-因雨雪、气温不能施工天数-其他原因停工天数。
计算过程中法定假日与因雨、气温停工日期重合未考虑;降雨次数不考虑,仅按连续降雨+停工天数考虑;其他原因停工未考虑;星期六和星期天考虑正常施工。
表1-1降雨影响下的正常施工天数
月份
施工项目名称
1月(天)
2月(天)
3月(天)
4月(天)
5月(天)