Doc Name Phase 2 Implementation Work Plan
Function Team
PHASE 2 TASKS AND SCHEDULE
TASK
DATE
POWER
LOCATION DELIVERABLES
USERS
Project preparation
Jan4-Jan11
Establish project team structure
Jan4-Jan7
Confirm the Accenture team members
Project Team List
Confirm the power users
Power Users List
Establish the roles and responsibilities
Roles and
Responsibilities
Set-up the project office
Jan7
LAN, fax, photocopier, telephone
FTP server
File cabinet, office utensils
Set-up SAP IDs
Jan7
Create IDs for new consultants
Mobilise orientate project team
Jan10
Conduc