Impact of Kick off Depth For the same target and BUR: The shallower the kick off depth, the lower the tangent angle and the shorter is the well length. Well KOP Angle Measured Depth @ TD Amount of directional steering 1000kop 1000ft 44 13077ft 2239ft 2000kop 2000ft 49 13395ft 2463ft 3000kop 3000ft 54 13777ft 2728ft 4000kop 4000ft 61 14242ft 3046ft 5000kop 5000ft 68 14418ft 3428ft 6000kop 6000ft 77 15522ft 3885ft 7000kop 7000ft 88 16400ft 4421ft * Shallow Kick off Point Shorter well length Lower casing costs, smaller rig capacity ? More directional work Inevitable if platform drilling, but ma