公路工程建设项目
交工检测方案
工程名称:XX市XX大道南延线近期方案工程施工
委托单位:XX建设集团有限公司
工程地点:
总页数(不含封面):共10页
XX市XX区建设工程质量安全监督检测中心
二○年月日
目录
一、工程概况······················································································2
二、检测依据······················································································2
三、检测方案······················································································3
四、主要仪器设备················································································4
五、拟投入的主要人员··········································································5
六、协调和组织人员·············································································5
七、进度安排及其他·············································································6
(一)综合安排·············································································6
(二)项目实施期间应急预案···························································6
(三)文明检测承诺·······································································6
(四)项目保密和保护所有权程序·····················································6
(五)废弃物管理措施····································································7
第1页共10页
XX市XX大道南延线近期方案工程施工工程交工检测方案
一、工程概况
本项目位于XX西北部的乐从镇,是对现状樵乐路进行拓建辅道,考虑到充分利用
现状旧路及避免拆迁,平面线形与现状樵乐路主线保持一致,不再另开通道,路线总
体呈南北走向,起点与正在建设的XX大道二期工程终点衔接,与樵乐路相交后向东延
伸与环镇西路相交后,路线转向南延伸,利用现状环镇西路,终点与XX一环南线相交,
路线全长4.57km。采用一级公路兼顾城市道路功能,双向六车道,设计速度80km/h;
辅道参照城市次干路标准进行设计,双向四车道,设计速度40km/h;现状环镇西路呈
南北走向,连接鹭杏线与XX一环南线,环镇西路为已建城市主干路,设计速度为60km/h,
双向六车道,路面为沥青混凝土路面,建成时间约1年,路况基本良好,本次施工直接
利用现状环镇西路,并维持现状城市主干路标准,仅对其局部进行改造。
本次改造主要针对樵乐路辅道、樵乐路与环镇西路交叉口、XX一环与环镇西路交
叉口进行整治。共有大桥1座,中小桥2座,人行天桥1座。樵乐路主路起止里程为
K21+930.656~K23+261.899,桩号方向为东往西,乐从往西樵方向,与本项目辅道桩
号方向相反。左幅道起点里程为LK0+000(=主路K23+0