St David’s 2 Shopping Centre A Project Case Study “St David’s 2” Shopping Centre Question 1. Draw a project network diagram of this project. Determine the shortest time to complete the project. Identify the critical activities. Task ID Task Description Duration (Months) Cost (£ Millions) Precedence A Planning and Consultation 9 12 - B Service Diversions 9 15 A C Highways Enabling 3 10 B D Appoint Main Contractor 3 4 A E CPO Inquiry 3 12 A F Obtain Government Approval 3 2 E G Construct John Lewis Store 24 36 C, D, F H Demolition 12 80 C, D, F I Main Scheme Construction 30 210 H J Refurbi