pmp考题模拟试题-完整英文版
概論 1-1-1:In comparing the Project Management Life Cycle and the Product Life Cycle, which of the followings is most true?
A:The project life cycle typically changes and evolves with the project.
B:The project management life cycle is unique to every project.
C:The project life cycle is can be referred to as the Project Management Life Cycle.
D:The product life cycle typically involves more than one project life cycle.
答案分析:
(D)The project management life cycle refers to project management process groups -initiating, planning, executing,controlling and closing. The project management cycle is applicable to each phase of the project life cycle. The Product Life Cycle typically involves more than one project,and therefore more than one Project Life Cycle.
概論 1-1-2:Which of the followings are not included in the main Project Management processes?
A:Feasibility
B:Executing
C:Planning
D:Closing
答案分析:
(A)Feasibility may well be an activity or stage within the project. The key point here is that it isnt one of the 5 recognized PMI Project Management processes.
概論 1-1-3:Which of the following statements is true?
A:Properly operated projects often go
through progressive elaboration,
not remaining fixed even though
the scope has been defined and agreed.
B:The project to create the Shanxia (Three-Gorges)Dam cant be considered temporary because of the operations such as power generation,transformation of electric power,transporation,etc. are following after the Dam has been completed.
C:Projects can go on indefinitely
when there is support and maintenance involved.
D:Projects are not unique because
there is always some aspect that
has been done before.
答案分析:
(A)Projects are unique and temporary.
Support and maintenance would not be part of the Project Life Cycle although it could be part of a product Life Cycle. The product may last a long time(e.g. Shanxia Dam)but the project to produce it was temporary. One of the natures of the project is that it has a definite beginning
您可能关注的文档
最近下载
- 自然辩证法-考试题库.doc
- 妇产科会阴擦洗冲洗护理技术.pptx
- 工程安全应急与响应预案.docx VIP
- Roland罗兰乐器JUNO-Gi 带数字录音功能的便携合成器JUNO-Gi Workshop 04 Realtime Control in the JUNO-Gi支持文档.pdf
- 《压疮压力性损伤的预防和治疗临床实践指南》解读.docx VIP
- 无热吸附式干燥机.doc
- 超星网课《中国古典小说巅峰-四大名著鉴赏》超星尔雅答案2023章节测验答案.doc
- 颊针疗法(基础篇).pptx
- 班会育人-心理健康课件——家校社协同育人,共创美好未来.pptx
- 同桌小伙伴(教学设计)-2024-2025学年岭美版(2024)美术一年级上册.docx VIP
文档评论(0)