施工总承包合同管理常见法律风险浅谈
施工总承包合同管理常见法律风险浅谈
摘要:面对复杂的市场环境,施工总承包单位要与发包人、分包人签订工程或分包合同,签约方由于合同签署时对可能承担的法律风险认识不足,在合同执行的过程中,一旦出现纠纷,往往会给合同签约一方造成难以挽回的损失,因此,要对合同管理中常见的法律风险有着清醒的认识。
关键词:合同管理、法律风险、防范、应付措施
Abstract: the face of a complex market environment, construction contract unit to with the developer, subcontractor signing the project or the subcontract, the parties to the contract signed the contract on the legal risk may be taking the lack of understanding of the execution of the contract, in the process, once appear, disputes, often can sign up for a party to the contract caused irreparable loss, therefore, to the contract management in common law has a clear understanding of the risk.
Keywords: contract management, legal risks, prevent, cope with measures
中图分类号:TU723.1 文献标识码:A文章编号:
-、风险概述
风险是指由于疏忽大意没有预见、或侥幸可以避免,而造成的难以克服、难以控制的客观情况。风险不是不可抗力,二者最大区别是:风险来源于疏忽大意、或者侥幸等主观过错;而不可抗力是没有主观过错。建筑工程合同是发包人与承包人之间为完成商定的建设工程项目,确定双方权利和义务的协议,如果合同签署时对可能承担的法律风险认识不足,往往会给签约一方造成难以挽回的损失。
二、常见风险分类
合同风险可以简单分为两类:
(一)、经营风险:指在经营活动中为了获得最大利润和效益而自愿加重责任、并通过自己的努力能够实现预定经营目标的情况。其特点是,经营风险与获得效益可能是成正比的,例如:施工单位愿意承担市场材料涨跌的风险以固定单价、或总价包干形式承接工程。
(二)、法律风险:在经营活动中出现的不受法律保护的行为,或者权利与义务极不平等、使自己始终处在只承担或多承担义务而不享有或少享有权利的情况。其特点是,法律风险一旦形成,就会使自己始终处于不利地位并必然遭受损失,而且这种不利局面和损失往往不能通??单方面继续履约来避免。例如同意承包商以个人名义签订劳务施工合同造成的法律风险,本文将着重就常见的几种法律风险及其防范应对措施进行探讨。
三、合同管理中常见的法律风险及防范
(一)、超越资质分包
案例:分包人以个人名义与总承包商签署分包或劳务合同,施工过程中出现因分包人拖欠工人工资、人员伤亡事故,工人将总承包告上法庭,法庭裁决由总承包商支付工人工资、赔偿工人损失。
我国《建筑法》第29条 “禁止总承包单位将工程分包给不具备相应资质条件的单位。”个人不能以法人名义签订合同,更不可能具备相应的资质条件。因此,承包单位与个人签署分包或劳务合同属于无效合同,总承包单位应承担其相应责任。
防范措施:
1、不以个人名义签署工程合同,建筑合同主体必须为独立的法人单位,或由独立法人单位组成的联合体。
2、不与超越本企业资质等级许可的业务范围承接任务的建筑施工企业或建筑劳务公司签订合同。
(二)、压缩合同工期的风险及其防范
案例:在中标或者合同订立后,发包人单方面要求压缩合同工期,承包人迫于发包人压力接受工期压缩条件,并签订补充协议或合同。
发包人此种行为从法律角度来讲是违法的,我国《招标投标法》第46条、第59条都规定,招标人、中标人订立背离合同实质性内容的协议的,责令改正;国务院《建设工程安全生产管理条例》第7条明确规定:建设单位“不得压缩合同约定的工期”。
防范措施:
当发包人提出的压缩合同工期的要求时,承包人可采取以下防范措施:
1、承包人有权拒绝压缩合同工期的要求;
2、在符合工程安全、质量等规范,并且制定了合理赶工措施的情况下,承包人可以与发包人签订赶工协议,同时承包人可以提出合理的赶工措施费用以