Now we come to the notice periods for permits for the different types of work. Major works on the forward programme need an application for a provisional authorisation at least 3 months before the job is planned to start on site. Then a full permit application is due 10 days before planned start. PAA explained on next slide A PAA is only required for major works and replaces the Section 55 notice under the NRSWA noticing system. The ‘booked’ space can be protected from any other planned activities. Any urgent works cannot, of course, be predicted, but anyone who has to carry out urgent wo