- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
桥梁限高架施工组织的设计
PAGE
PAGE 2
桥梁限高架施工组织设计
永煤公司铁路运输处
目 录
1 工程施工模式···············································································2
2 工程施工方案···············································································2
2.1 开工前交底及开工准备会························································2
2.2 钢结构制作················································································2
2.3 现场施工····················································································3
2.4 竣工验收····················································································3
3 限高架施工图纸···········································································4
4 施工安全措施···············································································7
4.1 一般要求····················································································8
4.2 钢轨搬动及运输安全································································8
4.3 钢架加工安全措施····································································8
4.4 用电安全····················································································8
4.5 基坑施工····················································································9
4.6 钢结构(钢轨)吊装安全························································9
5 施工所需机具、材料···································································9
4.1 施工所需机械、工器具····························································9
4.2 施工所需材料············································································9
6 工程概算·······················································································9
桥梁限高架施工组织设计
1 工程施工模式
该工程为车集线地销路立交桥、雪枫路立交桥的限高防护架施工,防护架使用43kg/m钢轨制作,由铁运处组织施工,具体分工为检修段负责按照图纸加工限高架,工务段负责限高架加工的监督和现场安装,供应科负责相关机具、材料的租用和购买。
施工负责人分别为:
检修段限高架制作负责人×××,分管领导×××。
工务段施工负责人:×××;分管领导×××。
主管科室管理人员:×××;负责领导×××。
2 工程施工方案
2.1 开工前交底及开工准备会:
运输科组织工程相关单位现场交底,确定限高架设置的详细位置(明确到具体尺寸)、高度。同时举行开工准备会,统一协调限高架制作与施工过程中的责任分工及注意事项,明确施工各工序检查和验收的步骤,确定开工时间。
2.2 钢结构制作:
钢结构制作前,工务段试验5根钢轨按图纸的布置方法和跨度安装后,其下垂量达到多少,以根据桥梁
文档评论(0)