V. Construction Site Coordination Management
Construction General Layout Plan Coordination
Based on construction deployment and milestone delivery requirements in various phases, General Contractor is in charge of formulating overall plan for general layout plan and deliver technical disclosure to subcontractors for carrying out dynamic management.
General contractor is responsible for dispatching road, temporary storage yard, fixed storage yard within construction site unitedly.
The subcontractor shall subnrt temporary access road or storage yard application
sheet to General contractor as p