南湖至大花岭联络线路基填筑施工试验段技术总结
[] : Mainly introduced the data collection , collation ,
analysis through the test section of the entire
construction process , to determine a reasonable
allocation of loose laying thickness 、the water content of
construction control 、the compaction number of achieve
compaction standard 、Rational allocation of machinery and
personnel , in order to guide the full range of subgrade
filling construction.
[Keywords] : Test section 、Loose laying thickness 、
Water cont