C2-01-1

单位工程施工组织设计

工程名称:伸马托斯卡纳三期二标段7#楼、8#楼工程

施工单位:黑龙江省东伟建筑安装工程有限企业

编制日期:2023年6月02日

目录

1工程概况····················································································1

2编制根据····················································································2

3总体布署····················································································4

4分项施工方案··············································································6

5质量确保技术措施·······································································54

6安全文明技术措施·······································································74

7确保工期技术措施·······································································85

8季节性施工措施··········································································87

9降低成本技术措施·······································································90

10十项新技术应用措施··································································92

11检验批划分··············································································96

12劳动力需求计划·······································································101

13主要机具设备计划····································································103

14施工进度计划··········································································104

15现场平面布置图·······································································106

1、工程概况

工程名称:伸马托斯卡纳三期二标段7#楼、8#楼工程

建设单位:黑龙江伸马房地产开发有限企业

设计单位:哈尔滨中建建筑设计有限企业

监理单位:黑龙江飞达建设工程管理有限企业

勘察单位:黑龙江寒地建筑勘察设计有限企业

施工单位:黑龙江省东伟建筑安装工程有限企业

1.1地理位置

托斯卡纳三期工程位于哈尔滨市利民开发区永达路,本工程地貌为松花江漫滩区,场地地形比较平坦,地势起伏不大,原自然地面高程在118.1~118.5m左右。地层岩性分布特征如下:第1层杂填土,第2层粉质粘土,第3层细砂,第4层中砂,第5层粗砂,第6层粉质粘土,第七层粗砂。

勘查期场地域地下水位埋深4.50m-6.00m,初见水位为5.00m-6.50m,具有微承压性;地下水主要靠大气降水及侧向径流补给,水位随季节变化影响,汛期水位较高,枯水期水位较低,年变幅在2-3M左右。

场地抗浮设计水位高程为116.00M考虑。

1.2工程类型、数量

本工程是由7#楼、8#楼构成,总建筑面积为14421.62m2。其中:7#楼及8#楼为高层住宅楼。

1.3构造形式、层数

本工程基础为超流态桩