C2-01-1
单位工程施工组织设计
工程名称:伸马托斯卡纳三期二标段7#楼、8#楼工程
施工单位:黑龙江省东伟建筑安装工程有限企业
编制日期:2023年6月02日
目录
1工程概况····················································································1
2编制根据····················································································2
3总体布署····················································································4
4分项施工方案··············································································6
5质量确保技术措施·······································································54
6安全文明技术措施·······································································74
7确保工期技术措施·······································································85
8季节性施工措施··········································································87
9降低成本技术措施·······································································90
10十项新技术应用措施··································································92
11检验批划分··············································································96
12劳动力需求计划·······································································101
13主要机具设备计划····································································103
14施工进度计划··········································································104
15现场平面布置图·······································································106
1、工程概况
工程名称:伸马托斯卡纳三期二标段7#楼、8#楼工程
建设单位:黑龙江伸马房地产开发有限企业
设计单位:哈尔滨中建建筑设计有限企业
监理单位:黑龙江飞达建设工程管理有限企业
勘察单位:黑龙江寒地建筑勘察设计有限企业
施工单位:黑龙江省东伟建筑安装工程有限企业
1.1地理位置
托斯卡纳三期工程位于哈尔滨市利民开发区永达路,本工程地貌为松花江漫滩区,场地地形比较平坦,地势起伏不大,原自然地面高程在118.1~118.5m左右。地层岩性分布特征如下:第1层杂填土,第2层粉质粘土,第3层细砂,第4层中砂,第5层粗砂,第6层粉质粘土,第七层粗砂。
勘查期场地域地下水位埋深4.50m-6.00m,初见水位为5.00m-6.50m,具有微承压性;地下水主要靠大气降水及侧向径流补给,水位随季节变化影响,汛期水位较高,枯水期水位较低,年变幅在2-3M左右。
场地抗浮设计水位高程为116.00M考虑。
1.2工程类型、数量
本工程是由7#楼、8#楼构成,总建筑面积为14421.62m2。其中:7#楼及8#楼为高层住宅楼。
1.3构造形式、层数
本工程基础为超流态桩
您可能关注的文档
最近下载
- AIAG 产品质量先期策划 第三版 _APQP (3rd edition) 纯中文版.pdf
- 垂直电梯的基础知识培训.ppt
- 管理学(北师大)中国大学MOOC慕课 章节测验 客观题答案.docx
- 4-技术中心职能.pdf VIP
- 永磁同步电动机电磁计算程序.xls
- 【茅庐学堂精选干货】63页PPT详解六个盒子组织诊断工具(附流程及关键点).pdf VIP
- 精品解析:浙江省绍兴市越城区2023-2024学年九年级上学期期末道德与法治试题(解析版).pdf VIP
- BCP计划(应急计划).doc
- 2023-2024年卫生管理(副高)考试高频题库(历年考点版)带答案解析.docx VIP
- 人教版初三化学各单元测试题及答案【精全册12套】.pdf VIP
文档评论(0)