St David’s 2 Shopping Centre A Project Case Study “St David’s 2” Shopping Centre Question 1. Draw a project network diagram of this project. Determine the shortest time to complete the project. Identify the critical activities. Project Network Diagram Activities A, B, C, H, I, M and Q are critical. The project duration is 69 months. Question 2. Convert the project diagram in a Gantt Chart. Schedule the non-critical activities as late as possible. Gantt Chart Question 3. Determine the most cost effective way to complete this project within 56 months given the following information Ste