St David’s 2 Shopping Centre
A Project Case Study
“St David’s 2” Shopping Centre
Question 1. Draw a project network diagram of this project. Determine the shortest time to complete the project. Identify the critical activities.
Project Network Diagram
Activities A, B, C, H, I, M and Q are critical. The project duration is 69 months.
Question 2. Convert the project diagram in a Gantt Chart.
Schedule the non-critical activities as late as possible.
Gantt Chart
Question 3. Determine the most cost effective way to complete this project within 56 months given the following information
Ste