运营管理 考试题库krajewski_om9_tif_SuppJ
Supplement
J
Operations Scheduling
TRUE/FALSE
Operations scheduling involves assigning jobs to workstations or employees to jobs for specific time periods.
Answer: True
Reference: Introduction
Difficulty: Easy
Keywords: operations scheduling, workstations, job assignments
Operations scheduling applies only to manufacturing, because services do not allow inventories.
Answer: False
Reference: Scheduling Service and Manufacturing Processes
Difficulty: Easy
Keywords: manufacturing, services, inventory
Makespan is the time of completion of a group of jobs, plus the starting time of the first job.
Answer: False
Reference: Scheduling Service and Manufacturing Processes
Difficulty: Moderate
Keywords: makespan, starting time
Makespan is the total amount of time to complete a single job or the first job in a group of jobs.
Answer: False
Reference: Scheduling Service and Manufacturing Processes
Difficulty: Moderate
Keyword: makespan, job
Utilization is the degree to which equipment, space, or the workforce is currently being used, measured as the ratio of average output rate to the maximum capacity .
Answer: True
Reference: Scheduling Service and Manufacturing Processes
Difficulty: Easy
Keywords: utilization, output rate, maximum capacity
Sequencing jobs does not affect tardiness, because processing times are unchanged with different sequences.
Answer: False
Reference: Sequencing Jobs
Difficulty: Easy
Keywords: sequencing of jobs, tardiness, processing time
A job shop is accompanied by divergent flows and low-to-medium volume output rates.
Answer: True
Reference: Sequencing Jobs
Difficulty: Easy
Keywords: job shop, flow, output rate
A manufacturer’s flow shop utilizes line or continuous flow processes.
Answer: True
Reference: Sequencing Jobs
Difficulty: Easy
Keywords: flow shop, line flow process, continuous flow process
Earliest due date (EDD) rule gives the job with the shortest processing time the highest priority.
Answer: False
Reference: Sequencing Jobs
Difficulty: