掏挖基坑开挖作业指导书
编码: TSFGC-04
目 次
1 适用范围 ································································································· 443
2 编写依据 ································································································· 443
3 作业流程图 ······························································································ 443
4 安全风险辨析与预控 ·················································································· 444
5 作业准备 ···································································································13
6 作业方法 ··································································································· 6·
7 质量控制措施及检验标准 ·············································································· 9·
1 适用范围
本节适用于 35kV 及以下配网工程架空线路工程的土质较好且地下水位低于基础
底面的掏挖基础基坑开挖。
2 编写依据
表 2 编 写 依 据
序号 引用资料名称
DL/T 5168—2002 《110kV~500kV 架空电力线路工程施工质量及评定规
1
程》
2 GB 50202—2002 《建筑地基基础工程施工质量验收规范》
3 Q/CSG 11105—2008 《南方电网工程施工工艺控制规范》
4 《中国南方电网有限责任公司基建工程质量控制作业标准( WHS )》
3 作业流程图
图 3 作业流程图
4 安全风险辨析与预控
4.1 掏挖基坑开挖作业前,施工项目部根据该项目作业任务、施工条件,参
照《电网建设施工安全基准风险指南》 (下简称《指南》)开展针对性安全风险评
估工作,形成该任务的风险分析表。
4.2 按 《指南》中与掏挖基坑开挖作业相关联的 《电网建设安全施工作业票》
(编码:TSFGC-04-01/01),结合现场实际情况进行差异化分析, 确定风险等级,
现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安
全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续
使用 10 天,超过 10 天须重新办理作业票,在工作完成后上交项目部保存备查。